Cascabel Working Group
A grassroots organization concerned with the cultural and ecological integrity of the lower/middle San Pedro Valley
<-- More Recent News


October 2015

  • Letter from Arizona Audubon to the ACC Line Siting Committee

  • Please consider and download our SunZia talking points for discussion with the Arizona Corporation Commission

September 2015

  • -->Let Your Voice Be Heard
    Finally, SunZia is moving to the Arizona Corporation Commission for their Certificate of Environmental Compatibility, the state permit needed to construct the project. Let your voice be heard !

    http://eservice.azcc.gov/Utilities/PublicComment*

    You must include the docket number, L-00000YY-15-0318-00171 (yes, that whole thing).

    *We've learned that web submission of comments is restricted to 1000 characters (not words!). Although better than nothing, it is preferable to submit your comments in writing (click here for details)



  • The Line Siting Committee hearing for the permit will be as follows. We'll be there!

    Willcox, October 19-21, Community Center
    Tucson, October 22-23, November 2-3, Tucson Convention Center
    Casa Grande, November 4-5, Holiday Inn
    Florence (if needed), November 16-20, Holiday Inn

    Details are available here, including all comment options, evening public comment periods, tour info, and how to access SunZia's application online. Anyone can attend the hearing and provide public comment, either at an evening session or at the beginning of each hearing day (except tour days).


  • The latest news from New Mexico: "SunZia Project still a Concern,"
    http://www.abqjournal.com/639686/opinion/sunzia-project-still-a-concern.html



March 2015


February 2015


January 2015

BLM Releases its Record of Decision (ROD) on the SunZia project, January 23rd―――――――――――――――

Other January News---
December 2014

November 2014
  • BLM releases the Environmental Impact Statement for the burial of SunZia's proposed lines across the northern part of the White Sands Missile Range



August 2014
"It must be built as a public works project if it is to be built. A private company will go bankrupt trying."     -Cascabel Working Group's co-chair, Mick Meader

from the Sante Fe New Mexican article Heinrich: Deal with feds paves way for SunZia transmission line


July 2014
  • SunZia unlikely to approved until early next year, if then:
    "...BLM would conduct a more in-depth supplement to the final environmental impact statement (EIS) that it released for the New Mexico-to-Arizona SunZia project in June 2013. A supplement to the final EIS could take as long as two years to complete, said Donna Hummel, a BLM spokeswoman in Santa Fe, N.M.

    Until the issue is resolved, a formal record of decision authorizing the project will not be issued, said Dave Goodman, planning and environmental coordinator in BLM's New Mexico State Office.

    A final EA that determines the next step for the transmission project that the Obama administration says is critical to developing wind and solar power in both states likely won't be completed until early next year, Goodman said.".
         -from eenews.net's Greenwire [subscription required]

June 2014


April 2014 March 2014 February 2014
FOIA Time!


January 2014
December 2013 November 2013 October 2013 September 2013 August 2013
July 2013
June 2013
May 2013
April 2013
March 2013


February 2013

  • SunZia: An Unnecessary High-Risk Project?
    A response to the report "Evaluating the SunZia Transmission Line Proposal A Guide for Stakeholders and Decision Makers "

    Some highlights:

    • The SouthWestern Power Group (SWPG) initially proposed SunZia to expand the markets for its permitted 1,000-megawatt power plant in S.E. Arizona, hoping to make it more economic, and SWPG yet intends to use SunZia for this purpose. The later expansion of SunZia did not diminish this need.

    • While New Mexico wind generation might help SunZia succeed, it alone cannot support a project of this scope. For the project to have any chance of success, natural gas generation must play a central role in it. Even combined, both forms of generation may be unable to support the project. This uncertainty makes the project’s economic outcome questionable.

    • When SunZia was conceived, it was thought that New Mexico’s renewable energy might help other states in the Southwest meet their renewable energy goals. However all states targeted for New Mexico’s renewable energy projects are now expected to meet and exceed their Renewable Portfolio Standard (RPS) requirements with their own resources, and SunZia is not needed to meet them. This is especially true for California. This makes long-distance transmission of renewables unnecessary, meaning that New Mexico’s solar and wind energy is far more likely to stay in New Mexico.

    • This analysis indicates that the methodology and economic analysis of the draft Environmental Impact Statement for SunZia is deeply flawed. The justification used in the draft EIS for SunZia is so incomplete that legal challenges may delay or stop the project. This possibility raises further questions about project’s viability.


    CWG's Mick Meader: "This is a highly tenuous and economically risky project, ...As proposed, it cannot be financed. The size of the project far exceeds the power needs in the region, and building a project merely to satisfy energy speculators does not make sense."

    Additional Conclusions of the Report:

    • Natural gas generation could easily come to dominate the project’s use, as SunZia would parallel the El Paso Natural Gas pipeline in southwestern New Mexico and southeastern Arizona for nearly 200 miles. In the last 11 years 1,045 megawatts of generation have been built along this pipeline and another 1,000 megawatts permitted. Given the enormous future projections for natural gas generation in the Southwest and the ease with which this existing generation can be expanded, the majority of the power eventually carried by SunZia could easily be natural gas generated.

    • The completion of the 570-megawatt Luna Energy Facility in Deming, New Mexico in 2006 eliminated any physical congestion on the transmission system in southwestern New Mexico, and SunZia is not now needed to increase power delivery in this region.

    • Building SunZia cannot be justified merely because New Mexico has abundant, high-quality renewable resources. All other western states, including Arizona, California, and Nevada, that might use New Mexico’s renewable energy have been developing their own capacity too quickly for New Mexico to gain control of the renewable transmission market and ensure sale of the state’s power.



  • Some local fun on a familiar topic:
    Highly Recommended --> just for fun

January 2013

  • CWG's Mick Meader has met in person with John Shepard, senior advisor for the Sonoran Institute, who is the principal author of their report released in November [see Dec 2012 news section].

    This report is misleading and damages efforts to show how this project may actually be used. It reinforces the BLM's and SunZia's mischaracterizations of the project as carrying mostly renewable energy rather than shows where they are wrong. The Sonoran Institute report was a huge undertaking requiring more than two month's of effort. It was backed by the full resources of the Sonoran Institute and given wide publicity with policy makers and the media.


Older News -->